SEWAGE TREATMENT PLANT – JEDDAH
الخدمة : Infrastructure
الوظيفة : محطات تحلية المياه
العميل : Saudi Company for Recreation Centers
Design review of existing design and Construction Supervision to increase the treatment capacity from 800 m³ /day to 3600 m³ /day in Phase-I and from 3600 m³ /day to 5400 m³ /day in Phase-II. The treatment plant was based on Activated Sludge Extended Aeration Process. The treatment also included Tertiary Treatment to produce effluent suitable for unrestricted irrigation. The project also included Power and Desalination plant.
COST: (SAR) 70,000,000
COMPLETION DATE:
1994
SERVICES :
• Design Review
• Construction Supervision
Salient Features
Capacity : 60,000 Cum
Process : Activated Sludge Extended Aeration
Tertiary Treatment